INLAND EMPIRE UTILITIES AGENCY (IEUA)
RP-1 OUTFALL RELOCATION AND UPSIZING
The RP-1 Outfall Relocation and Upsizing between Chino Ave and Riverside Project is located in Ontario, CA. The project consists of approximately 3,000 linear feet of 72-inch CML pipeline. The pipeline is intended to distribute reclaimed water.
Project was completed within the scheduled contract time of 240 calendar days.
When operational, the 72” reclaimed water line will accomplish the following:
- New Water Supply – delivery of over 30,000 acre-feet per year (AFY) of this local supply
- Enhances groundwater- improves the quality of the Chino Basin aquifer
- Drought proof supply- recycled water supply is not directly impacted by drought and could help mitigate the impacts of regional or statewide water supply limitations
- Reduce dependence of imported water supplies- increases local water supply reliability and decreases water imports from the Sacramento Bay Delta
Project Start: September 30, 2014
Project End: June 5, 2015
Project Value: $5,757,777